Thursday, September 29, 2011

Making Progress

After a bit of a slow start due to the wet weather last week we are really starting to make progress. We have accomplished a lot this week and both the contractors have been working long hours trying to make up for lost time. Here is a run down of what we have done this week.

1. The subgrade work and drainage have been installed on #17 green.

Kris' crew began installing the greens mix this afternoon. Our goal is to have the sod re-installed on #17 green on Saturday. There are a few steps that need to be completed before the sod can be laid, but we hope to accomplish it all tomorrow.  I will do my best to repost tomorrow or Saturday to show the rest of the process.

2. The irrigation crew has made tremendous progress. They have already completed all of #17 and #18, except for the greens loops which can not be performed until the green is ready for sod. They have also put the irrigation around the chipping green and putting green.


3. Along with all of installation work that has been completed, the first irrigation road crossing has been completed. This process is quite time consuming as precision is necessary when performing the work. The first step necessary is to hand dig out where all of the utilities are located such as power, cable, television, and fiber optic lines.

After the lines are exposed, a pit must be dug to accommodate the boring machine. This pit was dug approximately 5 feet deep to make sure that the bore was deep enough to allow for movement or directional changes that may occur if the drill bit hits rock while under the road. After the pit was dug, the boring machine was installed and set up.

After set up, the actual boring process began. 
After making it cleanly through to the other side the machine was removed and the sleeves were installed. First, an 8 inch steel sleeve was installed to protect the irrigation line and also because it provides a solid surface under the road as required by the DOT.
After the sleeve was installed, the irrigation line was run through the sleeve. Once this was done, the final necessary connections were made. The holes were then backfilled to complete the process.
As you can see, after a slow start we are in full swing now. I will follow up within the next day or two to show the rest of the green completion process.




Wednesday, September 21, 2011

Restoration Underway

After much anticipation we finally began the golf course restoration and irrigation system installation on Monday. Although this week hasn't been the best in regard to weather, we are off to a good start. Monday was very productive as a mobilizing day with numerous truckloads of irrigation pipe, supplies, and equipment arriving.

Tuesday both crews hit the ground running. All of the sprinkler head locations have been precisely marked, or "flagged" as we call it, for holes 17 and 18. They have also installed one row of irrigation thus far on #17. 

For the green construction work, we started on #17. After looking at the ground features, Kris marked out where the outer edges of the green surfaces were located (seen below in orange paint).

Kris' crew then began removing the sod from the green and the surround. After the sod was removed, the equimpent went to work removing all of the excess build up material. As they performed this work, the original green surfaces were identified by locating a firm clay layer below the organic buildup.


Although no work could be performed today on the course, we did have a very successful meeting. Kris Spence met with his assistant Nathan Cashwell, Steve Plummer, Bill Glenn, Dunlop White and myself to discuss the features of #17 and #18 greens. We were all in agreement of what was discovered and how we will be moving forward. As soon as the weather clears, the crews will pick up where they left off and keep pushing forward.

This has been a very exciting week for Roaring Gap Club. Now that we have begun, I will begin posting more frequently so be sure to check in and follow along as we work through our restoration!